Phase 1
Date: 11/02 – 5/03
Scope of Work
• Historical renovation
planning and
investigation
• Secure bell tower and
weathervane from large
scale deterioration
• Urgent preventative
repairs to roof and
flashing (east roof and
bell tower)
• Urgent preventative
repairs and
improvements to gutter
and storm drainage
COMPLETE |
Phase 2
Date: 4/04 – 7/06
Scope of Work
• Urgent preventative
upgrades to all
mechanical systems
(electric, lighting, and
lightning suppression)
• Urgent repairs to
exterior cast stone to
reduce falling debris
hazards
• Partial completion of
most urgent repairs to
paths, walkways,
handrails, and other
hazards
• ADA planning
• Partial completion of
ADA plan – improved
parking and accessibility
COMPLETE |
Phase 3
Target Date: TBD
Scope of Work
• Replace bell support and
improve belfry roof
• Preventative
Improvements to
building air circulation,
ventilation, and heating
• Preventative re-grading
and storm drainage
improvements to reduce
moisture
• Implementation of ADA
plan, likely to include:
wheel chair accessibility
to main sanctuary,
incremental parking, and
installation of accessible
bathrooms
• Completion of repairs to
paths, walkways, and
handrails
Estimate: $350,000
Funding not yet secured |
Phase 3
Target Date: TBD
Scope of Work
• Preventative
improvements to stained
glass windows
• Preventative restoration
of critical “at risk”
exterior detail elements
and stonework
• Cosmetic restoration of
exterior detail elements
• Cosmetic restoration of
interior decorative
stonework and plaster
• Restoration of
landscaping
• Restoration of various
artistic elements and
details
Estimate: $550,000
Funding not yet secured |